Forth Primary School

Forth Primary School will undergo construction of a new Kindergarten facility, providing state-of-the-art learning facilities from birth to 6 years old.

Current Status

Completion

Construction Commencement

2019

Expected Completion

2020

Funding

State Government - $900,000

Community Engagement

Engagement is now closed.

The initial stage of community engagement informs project initiation and site planning.

Thank you for your input.

Project Initiation and Planning

Project initiation and planning completed in 2018

The project initiation and planning stage informs development of a concept master plan.

Development of Master Plan

Development of the concept master plan has now been completed

Master plan

Community Engagement

Engagement is now closed.

This second stage of engagement provides opportunity for the community to review the concept master plan via the Department of Education website and other channels.

Design

Design completed in mid 2019

 

Construction

Construction works commenced onsite in July 2019

Completion

Construction of Forth Primary School Kindergarten was completed in February 2020