The Tasmanian Government has committed to the redevelopment of Hobart City High School, with $21.5 million allocated to provide contemporary facilities for students and staff. This included $1.5 million for early enabling works and $20 million for a major upgrade of the school.

Extensive consultation with students, staff and the broader community was undertaken to inform development of a long-term master plan for Hobart City High School. From this, a works plan has been developed to undertake the $20 million capital project.

Click to view the works plan and digital flythrough for Hobart City High School.

Photo of Hobart City High School

Timeline

The project initiation stage sees the commencement of project planning, documentation and engagement with the school community.

The project initiation stage sees the commencement of project planning, documentation and engagement with the school community.

This stage of community engagement informs development of the scope of works.

Click to view the draft master plan and the Community Engagement Outcomes Report.

Consultation is now closed.

This phase will see development of the stage 1 works site master plan and is expected to be completed in the second half of 2023.

The second stage of engagement provides opportunity for the community to review the approved works plan via this website and other channels.

Community engagement is now closed.

Click to view the works plan and digital flythrough for Hobart City High School.

Design development of the approved master plan in readiness for tendering and construction.

This is expected to commence in late 2023.

Construction is expected to commence in 2024.

Construction is expected to be completed in 2025.

Current Status

Design

Construction Commencement

2024

Expected Completion

2025

Funding

State Government - $21.5 million